Live Situation Bridges: 00:13 uur
Bridges
Today (0)
0%
Target: 16
Washing
Today (0)
0%
Target: 15
Inspection
Today (0)
0%
Target: 7
PTI
Today (0)
0%
Target: 124
Inzendingen
Date & TimeLocationDriverFinish
17 april 08:00Washing area 1Ibrahim09:10
17 april 07:21Bridge 3 Right (above)Ibrahim08:50
17 april 07:21Bridge 3 Right (under)Ibrahim08:50
17 april 07:07Inspection (loods side)Aneta11:10
17 april 06:56Washing area 4Ibrahim07:15
17 april 06:55Washing area 3Ibrahim07:15
17 april 06:41Inspection (middle)Ibrahim11:10
16 april 20:54Bridge 4 Left (above)Ibrahim06:45
16 april 20:49Bridge 4 Left (under)Ibrahim06:45
16 april 20:37Inspection (on depot)Aneta11:10
16 april 20:25Bridge 1 Right (under)Furkan07:10
16 april 20:09Bridge 2 Right (under)Furkan07:10
16 april 20:00Washing area 4Gabrielle21:30
16 april 20:00Washing area 3Gabrielle21:30
16 april 20:02Bridge 2 Right (under)Gabrielle21:30
16 april 20:00Bridge 1 Left (under)Furkan08:20
16 april 19:25Bridge 3 Right (under)Gabrielle19:48
16 april 19:23Bridge 2 Left (under)Gabrielle21:30
16 april 16:36Bridge 1 Right (under)Gabrielle21:30
16 april 19:20Bridge 4 Right (above)Ibrahim07:15
16 april 19:14Bridge 4 Right (under)Ibrahim07:15
16 april 17:38Inspection (middle)Gabrielle18:20
16 april 17:33Inspection (loods side)Gabrielle18:19
16 april 17:25Bridge 3 Left (above)Ibrahim08:40
16 april 17:20Bridge 3 Left (under)Ibrahim08:40
16 april 17:08Washing area 2Gabrielle21:30
16 april 17:08Washing area 1Gabrielle19:30
16 april 16:49Bridge 4 Left (above)Gabrielle19:05
16 april 16:48Bridge 4 Left (under)Gabrielle19:05
16 april 16:36Bridge 1 Right (under)Gabrielle21:30
16 april 16:04Bridge 2 Right (under)Gabrielle16:58
16 april 16:04Bridge 2 Right (under)Gabrielle17:00
16 april 16:02Bridge 1 Left (under)Gabrielle17:04
16 april 15:20Washing area 4Gabrielle15:44
16 april 15:20Washing area 3Gabrielle21:30
16 april 14:37Bridge 1 Right (under)Gabrielle15:31
14 april 20:24Inspection (middle)Gabrielle18:20
16 april 12:38Bridge 4 Right (above)Gabrielle15:27
16 april 12:35Bridge 4 Right (under)Gabrielle15:28
16 april 12:29Bridge 3 Right (above)Gabrielle16:54
16 april 12:27Bridge 3 Right (under)Gabrielle16:55
16 april 12:21Bridge 3 Left (above)Gabrielle14:40
16 april 12:18Inspection (on depot)Gabrielle18:21
16 april 12:14Bridge 3 Left (under)Gabrielle14:41
16 april 11:51Inspection (middle)Gabrielle18:21
16 april 11:46Inspection (loods side)Gabrielle18:22
16 april 11:21Washing area 1Ibrahim13:15
16 april 11:21Washing area 2Ibrahim13:15
16 april 10:14Bridge 2 Right (under)Ibrahim11:40
16 april 10:08Bridge 2 Right (above)Ibrahim11:40
16 april 09:25Washing area 3Ibrahim10:30
16 april 09:24Washing area 4Ibrahim10:30
16 april 08:20Inspection (loods side)Furkan10:15
16 april 08:13Bridge 4 Left (under)Ibrahim10:30
16 april 08:12Bridge 4 Left (above)Ibrahim10:30
16 april 08:07Bridge 2 Left (under)Ibrahim11:22
16 april 08:01Washing area 2Ibrahim08:50
16 april 08:01Washing area 1Ibrahim08:50
16 april 07:56Inspection (on depot)Okan11:20
16 april 07:52Inspection (middle)Furkan10:00
16 april 06:59Washing area 4Ibrahim08:30
16 april 07:00Washing area 3Ibrahim08:30
16 april 06:42LoodsIbrahim12:50
15 april 21:03Bridge 3 Right (under)Ibrahim10:00
15 april 21:01Bridge 3 Right (above)Ibrahim9:30
15 april 20:56Bridge 1 Right (under)Ibrahim11:20
15 april 20:55Bridge 2 Right (under)Furkan09:00
15 april 20:47Bridge 1 Left (under)Ibrahim11:20
15 april 20:30Washing area 1Gabrielle21:14
15 april 20:31Washing area 2Ibrahim06:30
15 april 20:07Bridge 3 Left (above)Ibrahim08:20
15 april 20:03Bridge 3 Left (under)Ibrahim8.35
15 april 19:47Bridge 4 Right (under)Ibrahim7.35
15 april 19:42Bridge 4 Right (above)Ibrahim7.35
15 april 19:36Bridge 4 Left (above)Gabrielle20:59
15 april 19:37Open loodsNick20:30
15 april 19:28Open loodsNick20:00
15 april 19:33Washing area 4Gabrielle20:28
15 april 19:32Bridge 4 Left (under)Gabrielle20:58
15 april 19:31Washing area 3Gabrielle19:54
15 april 19:20Open loodsNick18:30
15 april 19:14Bridge 2 Left (above)Nick19:00
15 april 19:11Bridge 2 Left (under)Nick20:00
15 april 16:56Washing area 2Nick19:12
15 april 16:54Washing area 1Gabrielle17:52
15 april 15:50Open loodsNick18:00
15 april 15:10Inspection (on depot)Nick19:00
15 april 14:51Washing area 4Stefan17:00
15 april 14:51Washing area 3Gabrielle15:50
15 april 14:13Washing area 2Stefan16:00
15 april 14:13Washing area 1Gabrielle15:50
15 april 13:52Bridge 4 Right (above)Gabrielle16:39
15 april 13:52Bridge 4 Right (under)Gabrielle16:38
15 april 13:24Bridge 3 Right (above)Nick19:00
15 april 13:22Bridge 3 Right (under)Nick19:00
15 april 12:32Bridge 4 Left (under)Gabrielle15:11
15 april 12:32Bridge 4 Left (above)Gabrielle15:11
15 april 12:09Washing area 3Gabrielle15:53
15 april 12:08Washing area 4Gabrielle13:53
15 april 11:35Inspection (middle)Nick19:00
Date & TimeLocationDriverFinish